QA

Quick Answer: When To Bull Float Concrete

Bull floating is performed on freshly poured concrete during the initial finishing process before surface water, called bleed water, appears. Floating with a hand or power float, is a final finishing procedure performed after the bleed water has dried.

When should you bull float concrete?

Concrete Bull Floats and Darbies. Darbying or bull floating should be done immediately after “screeding”, or after the concrete has been tamped if tamping was done. This process should be finished before excess moisture or bleedwater appear on the surface.

When should you Powerfloat?

A useful guideline to know when you can start up your trowel, is when the operator can stand on the concrete surface, and leave footprints about 1/8”-1/4” in depth and you can walk on it firmly without the top layer sticking to your boots it is ready to power float.

What may occur if a slab is floated too soon?

More often, premature finishing or improper first (bull floating) or second floating results in trapping rising bleed water and air below the top surface of the concrete (Image 2). When this occurs, the resulting weak or soft zone below the surface causes the top surface of the concrete to flake or scale off.

How long does it take concrete to fully cure?

Concrete typically takes 24 to 48 hours to dry enough for you to walk or drive on it. However, concrete drying is a continuous and fluid event, and usually reaches its full effective strength after about 28 days.

How many times do you float concrete?

For a really smooth finish, repeat the troweling step two or three times, letting the concrete harden a bit between each pass. At first, hold the trowel almost flat, elevating the leading edge just enough to avoid gouging the surface.

Can you pour concrete in two stages?

Yes the Concrete is weakened at the joint because of the bonding process. This can definitely weaken a concrete pour. This type of joint is referred to as a cold joint.

What if it rains after pouring concrete?

If the rain begins 2 to 4 hours after pouring the concrete, the surface will not be damaged. Similarly, if it rains soon after the finishing stage, rainwater will not cause much damage if it does not seep into the surface. Light sprinkles of rain can cause no damage to freshly prepared concrete structures.

Can you smooth out concrete after it dries?

Sand the Surface and Wash the Concrete Finish by fine-tuning with light sandpaper, until the surface is perfectly smooth. We recommend using a hand planer to smooth and compact the surface. If the concrete dries a lot then we recommend that you add water to the surface, this will help you give it a good finish.

How long should concrete cure before removing forms?

The forms or “molding” that holds the concrete in place until it dries should be left alone for at least two days to ensure that the concrete is completely dry. If the forms are removed too soon, the concrete can begin to sag, crack and collapse, especially if conditions like temperature affected its strength.

How many times should you power trowel concrete?

It is recommended to run the trowel at three fourth of its speed, while you are floating the concrete and keep the blades flat. Keeping the blades will also keep the machine from digging into the concrete and ruining all the progress you have made.

Why do you trowel concrete?

With every concrete pour troweling is important, because it allows the concrete to continue the process of finishing the concrete and squeezing residual water out of the concrete. Removing any excess water out of the concrete decreases the chances of the concrete cracking.

Can you just bull float concrete?

A bull float is used to level and smooth freshly poured concrete. Concrete used for visible projects, such as driveways, patios and sidewalks, often requires finishing. A bull float is a tool used for finishing concrete.

What happens if you dont trowel concrete?

If you haven’t done this before or only done it a few times you are likely to make two mistakes; troweling too soon and troweling too much. Both of these have the effect of pulling fines and water to the surface. This can lead to a weakened surface, tiny cracks and a white dusty surface.

Does troweling make concrete stronger?

^ With each successive troweling, increase the angle of the blade (maximum should not exceed more than 1″ [2.5cm]). On each successive pass the angle is slightly increased to exert greater pressure on the hardened surface. The increased blade pressure provides a dense, durable concrete surface.

Can you drive on concrete after 3 days?

Concrete professionals suggest waiting at least seven days after the crew is finished before parking or driving your personal vehicle(s) on your new concrete. The reason for this is because one week is the time period it takes for your new concrete to achieve 90% of its full potential strength.

How strong is concrete after 3 days?

Thus, it is clear that concrete gains its strength rapidly in the initial days after casting, i.e. 90% in only 14 days.Why do we test concrete compressive strength after 28 days? Age Strength per cent 1 day 16% 3 days 40% 7 days 65% 14 days 90%.

What happens if you dont water concrete?

Concrete strength depends on the growth of crystals within the matrix of the concrete. These crystals grow from a reaction between Portland cement and water-a reaction known as hydration. If there isn’t enough water, the crystals can’t grow and the concrete doesn’t develop the strength it should.

How long should concrete cure before putting weight on it?

Curing time of concrete is typically 24-48 hours, at which point it’s safe for normal foot traffic. After one week, concrete is typically cured enough to handle continued construction including heavy machinery.